企业资源过程控制管理系统建设项目
系统测试方案
1 / 8word.
目 录
1. 概述····························································································································· 3 1.1 编写背景 ····················································································································· 3 1.2 读者对象 ····················································································································· 3 2. 测试方案 ····················································································································· 4 2.1 测试模块及部门 ·········································································································· 4 2.2 测试数据 ····················································································································· 5 2.3 测试策略 ····················································································································· 5 2.4 测试人员 ····················································································································· 6 2.5 测试计划 ····················································································································· 7 2.6 测试跟踪 ····················································································································· 8 2.7 测试通过准则 ·············································································································· 8 2.8 测试技术支持 ·············································································································· 8
2 / 8word.
1. 概述
1.1 编写背景
企业资源过程控制管理系统是采用美国IBM公司的Maximo平台。项目实施按照“统一规划、分布实施”的原则,前期项目经过了现场需求调研、系统设计、系统开发等阶段。 本次编写本测试方案的目的是为软件开发项目管理者、项目关键用户、项目最终用户、软件工程师、系统维护人员等,进行单元、联动集成式测试,目的是对大连发电公司管理信息系统在业务流程、模块功能等方面进行熟悉和测试,相关人员在进行系统测试时,对不符合项进行及时提至项目组或项目各组长。项目组将对相关人员在系统测试中发现的问题进行改进和完善。
1.2 读者对象
本测试方案的合法读者对象为软件开发项目管理者、项目关键用户、软件工程师、系统使用者。
3 / 8word.
2. 测试方案
2.1 测试模块及部门
单元测试:
测试模块 操作票管理 操作票管理 标准操作管理 值班记事综合查询 值长值班记事 #1号汽机值班记事 #2号汽机值班记事 #1号锅炉值班记事 #2号锅炉值班记事 #1号电气值班记事 运行管理 #2号电气值班记事 燃运值班记事 化学精处理值班记事 化学汽水值班记事 化学氢站值班记事 化学水处理值班记事 化学循环水值班记事 除灰值班记事 脱硫值班记事
4 / 8word.
测试部门 运行部
联动测试:
测试模块 缺陷创建 缺陷管理 缺陷查看 缺陷跟踪 电气第一种工作票 电气第二种工作票 工作票管理管理 热力机械工作票 热控设备工作票 动火工作票 测试部门 运行部 检修维护分场、生技部 运行部、检修维护分场、生技部、安监部 2.2 测试数据
系统生产运行模块的基础数据主要有人员信息数据、权限信息、设备信息数据、标准两票数据以及业务流程中涉及的标准数据。
相关人员在测试中发现基础数据不完善的地方需要及时反映,辅助软件开发方完善基础数据。
2.3 测试策略
系统测试分为单元测试、系统联动测试。以下根据不同阶段测试的侧重点不同,分别介绍测试策略:
单元测试
单元测试根据管理信息系统、子系统、模块进行划分,测试最终的功能模块是单独的部门、专业和班次。例如运行操作票管理,从创建票、审批、执行、结束,都在本部门相关人员的配合下完成,与别的部门班组没有交错的业务联系的
5 / 8word.
情况下称之为单元测试。单元测试是对功能模块进行正确检验的测试工作,也是后续测试的基础。
联动测试
联动测试也叫系统集成测试。通常在单元测试的基础上,需要将所有的模块按照设计要求集成为系统,再在系统的层面上进行整体的测试。例如:电气第一种工作票的创建、工作票签发、运行接票、值长批准、安措办理、许可开工、工作票完工、合格检查、工作票终结等。各个流程节点在单元测试基础上都无问题时再进行联动的测试。
2.4 测试人员
本次系统联动测试涉及人员如下:
缺陷模块:
生产技术部:汽机、锅炉、电气、化学、土建、热工、燃料、脱硫等专业专工。
运行部:为发电运行分场、除灰脱硫分场、燃料运行分场,涉及专业人员为汽机、锅炉、电气、化学、燃运、除灰、脱硫各专业岗位人员。
检修维护分场:涉及专业为汽机、锅炉、电气、化学、燃料、除灰、脱硫各专业岗位人员。
工作票模块:
运行部:发电运行分场、除灰脱硫分场、燃料运行分场,涉及专业人员为汽机、锅炉、电气、化学、燃运、除灰、脱硫各专业具有工作票接票人、许可人权限以上人员。
检修维护分场:涉及专业为汽机、锅炉、电气、化学、燃料、除灰、脱硫各专业工作票负责人。
6 / 8word.
操作票模块:
运行部:发电运行分场、除灰脱硫分场、燃料运行分场,涉及专业人员为汽机、锅炉、电气、化学、燃运、除灰、脱硫各专业副值以上权限人员。
2.5 测试计划
目前项目组已经对各运行、检修分场的相关人员进行了培训。并下发了系统地址和员工工号进行单元测试,系统操作手册等。测试计划具体如下:
单元测试
测试模块 测试部门 测试要求 可按操作票管理进行操作流程进行创建、审批、打印。 操作票管理 运行管理 运行分厂、燃料运行分厂、除脱运行分厂 运行各分厂按班次、专业进行运行交接班、记事等操作,至少需要运行5个值别能完整操作一个循环。
联动测试
测试模块 测试部门 测试要求 缺陷管理 运行分厂、燃料运行分厂、除脱运运行分厂、燃料运行分行分厂的各班次分专业填写1-5类厂、除脱运行分厂、检缺陷单,发至检修分厂填写检修结修维护分场、生技部 果,然后发至各运行分厂和生技部进行验收。 运行分厂、燃料运行分由各检修分厂根据缺陷单创建4种工作票管理管理 厂、除脱运行分厂、检工作票发、签发至对应的运行分厂修维护分场、生技部、进行接票、批准、开工、终结,形7 / 8word.
安监部 成工作票管理流程的闭环。 2.6 测试跟踪
流程测试过程中由软件厂方工程师同发电公司信息中心人员进行现场跟踪指导,并记录流程进行过程中所发现的问题,对重大问题需要经过双方探讨确认进行修改。
2.7 测试通过准则
怎样判定集成测试过程完成了,可按以下几个方面检查:
1、成功地执行了测试计划中规定的所有测试内容; 2、熟练操作使用系统模块; 3、信息中心和项目组的评审。
2.8 测试技术支持
联系地址:
联系电话: